Greetings, everyone!
Thank you all for being so patient and considerate to everyone involved in the reconstruction of Woodland Avenue. As the construction season winds down, a lot has been accomplished in the last few weeks. The remaining work for this season will be completed this week.
Progress
Ulland has completed all utility work and has rebuilt the roadway up to Norton Street. Last week, the concrete curb & gutter was placed from Griggs Place to Norton Street and the last lift of blacktop was paved from Kent Road to Clover Street. Earlier this week, the sidewalk and driveways were being replaced.
Schedule
Ulland is currently working on the base course of blacktop from Griggs Place to Norton Street. This will be complete on Wednesday, 10/28/09. They will pave the final lift of blacktop on Wednesday and Thursday of this week. AJ’s Landscaping will finish the sod and yard restorations. Blacktop driveways will be restored on Thursday, 10/29/09. Ulland will stripe the roadway and install traffic signs, and we anticipate lifting the detour within a week.