Progress

Ulland has completed all underground utility work for Phase I of the construction.  They have also finished subcutting from Griggs Place to Norton Street.  They are currently backfilling this area with sand and class 5.  Landscaping has been done between Clover Street and Griggs Place.  The curb & gutter and sidewalk is complete up to Griggs Place.

Schedule

Week of 10/12:  Continue backfilling road subcut; pave base course from Clover Street to Griggs Place.

Week of 10/19:  Finish concrete curb & gutter and remaining driveways; place remaining base course from Griggs Place to Norton Street.

Week of 10/26:  Finish landscaping; place bituminous wear course; project clean-up.

Week of 11/2:   Remove detour; open roadway to public.