Greetings, everyone!

Salo Engineering, the City of Duluth, and Ulland Brothers are continuing their efforts to improve your neighborhood and business community.  We thank all residents and business owners for your support and patience during the construction season.

Progress
To date, Ulland has progressed quite well despite the rains in July and encountering ledge rock.  All the sanitary sewer mains have been installed.  The watermain is complete, with the exception of the crossing at Elizabeth Street.  Storm sewer work and curb & gutter up to Griggs Place are complete.

Remaining Schedule

Week of 9/21/09:    Ulland to continue on storm sewer work between Norton and Elizabeth Streets, place sidewalks from Clover Street to Griggs Place, shape class 5 for paving, and place water & sanitary services from Griggs Place to Norton Street.  During this week, Ulland will be working on the storm sewer between St. Marie and Norton Streets.  This will require Woodland Avenue to be closed between those streets for 2-3 days.  Traffic will be able to cross Woodland Avenue at Norton Street, with a half-day closure to bring storm sewer across the intersection.  There will be temporary bituminous, curb, and sidewalk placed in this area, which will be removed next spring and rebuilt with the new roadway.

Week of 9/28/09:    Finish all storm sewer and utility services, pave bituminous from Griggs Place to Clover Street, and subcut roadway from Griggs Place to Norton Street.

10/5/09 – 10/30/09      Complete curb & gutter, sidewalk, bituminous paving, and landscaping up to Norton Street.

11/1/09    Project under winter suspension and detour route is lifted.

5/1/10      Construction resumes and detour route is back in place.