Progress

During the last 2 weeks, Ulland has been working on the sanitary sewer main and watermain between Griggs Place and Norton Street.  The sanitary main is complete in this area, and the watermain is scheduled to be complete by September 11, 2009.  The intersection of Clover Street and Woodland Avenue has been opened, and the signal system is operational.

Schedule

Following is an update of the remaining schedule:

September 8-12:  Ulland will finish watermain work up to Norton Street and begin placing water and sewer services from Griggs Place to Norton Street.

September 14-19:  Storm sewer will be placed from Elizabeth Street to St. Marie Street.  Hovland Masonry will place curb & gutter and sidewalk from Clover Street to Griggs Place.  The high pressure watermain crossing at Elizabeth Street will be done.  We will notify affected parties 48 hours in advance of the watermain shutdown.

September 21-26:  Ulland will be rebuilding the roadway from Griggs Place to Norton Street.

September 28 - October 24:  Remaining curb & gutter and sidewalks will be placed, along with bituminous paving and landscaping.

The contractor has a completion date of November 1, 2009 for this segment of the project.