Wed 19 Aug 2009
Progress
This past week, ledge rock was encountered in the sanitary sewer trench between Elizabeth and Norton Streets. Ulland continues to move slowly through the rock section with the sanitary sewer. In addition, Ulland has begun placing watermain from Griggs Place north toward Elizabeth Street. We anticipate some small disruptions in water service between Elizabeth and St. Marie Streets. All affected parties will be notified at least 24 hours in advance of any disruption. Salo Engineering and the City of Duluth Engineering Department continue to keep the Duluth Fire Department informed about accessibility to the east end of Elizabeth Street. At the request of several business owners, we ordered a construction sign with all business names in the Mount Royal Center. This sign will be displayed at the intersection of St. Marie Street and Woodland Avenue. As construction progresses toward St. Marie Street, the sign will be moved accordingly.
Schedule
There are no changes to the project schedule posted last week.