Progress:
Hovland Masonry placed curb from Kent Road to the south side of the Clover Street intersection.  Ulland finished the select granular borrow and graded the class 5 for curb between Kent Road and Clover Street.  The sanitary sewer is complete from Kent Road to Griggs Place.  The watermain is complete to just north of Griggs Place.  The storm sewer is complete from Kent Road to Clover Street.  Work is continuing to the north.  API Electric set the cameras at the Clover Street and Kent Road intersections, and they completed Qwest’s conduit through the Clover Street intersection.  A solar lighted sign (”Caution Hidden Driveway”) was installed on Wallace Avenue.

Schedule:
Ulland is currently backfilling behind the curb and placing forms for the new sidewalks.  The sidewalks will be placed on Friday, July 24th.  Bituminous paving of the street will take place on Thursday, July 30th.  They are continuing with the work on the storm sewer and placing services between Clover Street and Griggs Place.  Ulland is on schedule to begin work at the Norton Street intersection on Monday, August 3rd.  New business and access signs will be erected by then for Phases 3-5 (Norton Street to Griggs Place).  As always, the schedule is dependent on the weather.