Progress:
Hovland Masonry placed curb from Kent Road to the south side of the Clover Street intersection. Ulland finished the select granular borrow and graded the class 5 for curb between Kent Road and Clover Street. The sanitary sewer is complete from Kent Road to Griggs Place. The watermain is complete to just north of Griggs Place. The storm sewer is complete from Kent Road to Clover Street. Work is continuing to the north. API Electric set the cameras at the Clover Street and Kent Road intersections, and they completed Qwest’s conduit through the Clover Street intersection. A solar lighted sign (”Caution Hidden Driveway”) was installed on Wallace Avenue.
Schedule:
Ulland is currently backfilling behind the curb and placing forms for the new sidewalks. The sidewalks will be placed on Friday, July 24th. Bituminous paving of the street will take place on Thursday, July 30th. They are continuing with the work on the storm sewer and placing services between Clover Street and Griggs Place. Ulland is on schedule to begin work at the Norton Street intersection on Monday, August 3rd. New business and access signs will be erected by then for Phases 3-5 (Norton Street to Griggs Place). As always, the schedule is dependent on the weather.
Construction of the watermain is complete between Clover Street and Griggs Place. The contractor will continue working on the sanitary sewer and storm sewer in this segment for the remainder of the week. The road-building process has begun to take shape between Kent Road and Clover Street. Class 5 is being placed, and curb & gutter is anticipated next week. Bituminous surfacing will follow. The contractor is on schedule to open Woodland Avenue between Kent Road and College Street on August 1, 2009.
We are anticipating that the contractor will start working on the Norton Street to Griggs Place segment, Phases 3-5, on or about July 27, 2009. The anticipated schedule is as follows:
July 27 New traffic signage will be placed beginning at 6:00 a.m.
July 27-28 Bituminous and concrete removal from Norton Street to Griggs Place.
July 28-Aug 3 Temporary water service and new watermain installation.
Aug 3-14 Sanitary sewer main, water and sewer services installation.
Aug 18 Tentative Informational Meeting
Aug 17-28 Storm sewer installation - St. Marie Street to Griggs Place.
Aug 31-Sept 11 Roadway Reconstruction
There will be some temporary water shut-offs during the watermain reconstruction. There will be 24 hours’ notice when these shut-offs occur. Access across Elizabeth Street will be open during business hours, 7:00 a.m. to 5:00 p.m. The contractor will be doing all utility work after 5:00 p.m. or on a Saturday. Once the roadway work begins, the intersection will be done half at a time with one lane of traffic open.
The bituminous and concrete removal between Clover Street and Griggs Place has started and will be finished this week. The Contractor will follow this with reconstruction of the utilities in the same area during the next two weeks. The subcut and granular backfill is complete between Kent Road and Clover Street. During the week of July 13, this segment will see the completion of the gravel and construction of the concrete curb. Paving will follow shortly thereafter. We are on schedule to open the segment between Kent Road and College Street by August 1, 2009. We anticipate that the Contractor will begin Phases 3-5 starting at the Norton Street and Woodland Avenue intersection sometime between July 15 and 20.
A resident meeting is scheduled for 8:30 a.m., Tuesday, July 14, at the Mount Royal Fine Foods cafeteria. Businesses, residents, and facility managers are invited to attend this meeting. We will present details on the Contractor’s activities, detour routes, and access to your homes and businesses. We look forward to seeing you there.