		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=80</link>
		<comments>http://saloeng.com/blog/?p=80#comments</comments>
		<pubDate>Fri, 06 Aug 2010 16:47:33 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=80</guid>
		<description><![CDATA[Greetings, Everyone!
We are now halfway through the 2010 construction season.  After working through the contaminated soil in the intersection of St. Marie Street and Woodland Avenue, we have finally placed curb &#038; gutter and sidewalk and paved this area.  This has allowed us to move into Phase II of the 2010 detour route, which directs [...]]]></description>
			<content:encoded><![CDATA[<p>Greetings, Everyone!</p>
<p>We are now halfway through the 2010 construction season.  After working through the contaminated soil in the intersection of St. Marie Street and Woodland Avenue, we have finally placed curb &#038; gutter and sidewalk and paved this area.  This has allowed us to move into Phase II of the 2010 detour route, which directs traffic from Arrowhead Road to Wallace Avenue to St. Marie Street and then back to Woodland Avenue.</p>
<p><u>Remaining Work Schedule</u>:  Ulland Brothers will continue working on water and sewer services and then move to the storm sewer.  This work will take about 4 more weeks.  After that, they will begin rebuilding the roadway and finally concrete and landscaping.   We are anticipating a completion date of early October.</p>
<p>A reminder that we continue to hold weekly construction meetings on Tuesdays at 9:00 a.m. at the intersection of St. Marie Street and Woodland Avenue.  If anyone has any questions, please contact David Bolf at 727-8796.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=80</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=68</link>
		<comments>http://saloeng.com/blog/?p=68#comments</comments>
		<pubDate>Tue, 25 May 2010 12:40:10 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=68</guid>
		<description><![CDATA[Greetings, everyone!
The 2010 construction season is now upon us.  A reminder to all that Stage 2 (2010) construction has been broken into two phases: Phase 1, Norton Street through the St. Marie Street intersection, and Phase 2, St. Marie Street to Arrowhead Road.  We have planned a detour route for each of these phases.  A [...]]]></description>
			<content:encoded><![CDATA[<p>Greetings, everyone!</p>
<p>The 2010 construction season is now upon us.  A reminder to all that Stage 2 (2010) construction has been broken into two phases: Phase 1, Norton Street through the St. Marie Street intersection, and Phase 2, St. Marie Street to Arrowhead Road.  We have planned a detour route for each of these phases.  A map of the detour routes can be seen by clicking the &#8220;Detour Routes&#8221; link to the right.</p>
<p>Ulland Brothers resumed construction the week of May 3rd this year.  Shortly after getting started, we encountered some contaminated soil in the intersection of St. Marie Street and Woodland Avenue.  In an effort to keep construction activities moving along, we decided to move into Phase 2 of the construction.  Ulland has started with the new sanitary sewer at the intersection of Bruce Street and Woodland Avenue.  Ulland plans to continue with the sanitary sewer on Phase 2 until it is complete.  A second crew will be starting this week at the location of the contaminated soil.</p>
<p>Originally, we had an intermediate completion date of July 17, 2010 for Phase 1.  This may be pushed out a week.  The final completion date remains the same, September 25, 2010.  We will be holding our weekly construction meetings at 9:00 a.m. on Tuesdays near the St. Marie Street intersection.  If you have questions or concerns, please feel free to attend.  Meeting minutes will be posted weekly.</p>
<p>If anyone has any questions, comments, or concerns, please contact David Bolf or David Salo with Salo Engineering at (218) 727-8796.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=68</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=65</link>
		<comments>http://saloeng.com/blog/?p=65#comments</comments>
		<pubDate>Thu, 19 Nov 2009 15:12:59 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=65</guid>
		<description><![CDATA[The construction season is now over.  Despite an extremely wet October and the presence of ledge rock, we were able to complete Stage 1 of the project by November 6.  This is within one week of the original completion date of November 1.  The Contractor has removed all traffic control and detour signs until next [...]]]></description>
			<content:encoded><![CDATA[<p>The construction season is now over.  Despite an extremely wet October and the presence of ledge rock, we were able to complete Stage 1 of the project by November 6.  This is within one week of the original completion date of November 1.  The Contractor has removed all traffic control and detour signs until next May.  The one exception is the stop sign at 4th Street and 24th Avenue East.  This is a temporary sign that will remain through the winter and 2010 construction.</p>
<p>Ulland&#8217;s schedule for next year includes resuming construction in mid-May, once the road restrictions are lifted.  At that time, we will place the detour route as we had it this year.  The detour will remain in place until work is complete through the intersection with St. Marie Street.  We will then move the detour to Wallace Avenue from Arrowhead Road to St. Marie Street.  At that point, Woodland Avenue from 4th Street to St. Marie Street will be open.</p>
<p>As spring approaches and construction comes closer, we will be updating this blog with a start date and schedule.  We will also be holding a resident/business meeting to discuss the 2010 construction schedule.<br />
Salo Engineering, the City of Duluth, and Ulland Brothers would like to extend our appreciation and thanks for everyone&#8217;s patience throughout the project.  The open communication between owners/businesses and the construction team allowed for a successful and safe project.  We look forward to being back in your neighborhood next year to complete Stage 2 of the project.</p>
<p>If anyone has any comments, questions, or concerns, please notify David Bolf or David Salo with Salo Engineering at (218) 727-8796.</p>
<p>See you next year!
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=65</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=61</link>
		<comments>http://saloeng.com/blog/?p=61#comments</comments>
		<pubDate>Tue, 27 Oct 2009 20:14:10 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=61</guid>
		<description><![CDATA[Greetings, everyone!
Thank you all for being so patient and considerate to everyone involved in the reconstruction of Woodland Avenue.  As the construction season winds down, a lot has been accomplished in the last few weeks.  The remaining work for this season will be completed this week.
Progress
Ulland has completed all utility work and has rebuilt the [...]]]></description>
			<content:encoded><![CDATA[<p>Greetings, everyone!</p>
<p>Thank you all for being so patient and considerate to everyone involved in the reconstruction of Woodland Avenue.  As the construction season winds down, a lot has been accomplished in the last few weeks.  The remaining work for this season will be completed this week.</p>
<p><u>Progress</u></p>
<p>Ulland has completed all utility work and has rebuilt the roadway up to Norton Street.  Last week, the concrete curb &#038; gutter was placed from Griggs Place to Norton Street and the last lift of blacktop was paved from Kent Road to Clover Street.  Earlier this week, the sidewalk and driveways were being replaced.</p>
<p><u>Schedule</u></p>
<p>Ulland is currently working on the base course of blacktop from Griggs Place to Norton Street.  This will be complete on Wednesday, 10/28/09.  They will pave the final lift of blacktop on Wednesday and Thursday of this week.  AJ&#8217;s Landscaping will finish the sod and yard restorations.  Blacktop driveways will be restored on Thursday, 10/29/09.  Ulland will stripe the roadway and install traffic signs, and we anticipate lifting the detour within a week.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=61</wfw:commentRss>
		</item>
		<item>
		<title>NOTICE</title>
		<link>http://saloeng.com/blog/?p=60</link>
		<comments>http://saloeng.com/blog/?p=60#comments</comments>
		<pubDate>Fri, 23 Oct 2009 20:40:15 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=60</guid>
		<description><![CDATA[Ulland Brothers will be paving the wear course on Woodland Avenue tomorrow morning, 10/24/09, between Kent Road and Clover Street.  This section of road will be closed during the morning and should be back open around 1:00 p.m.

]]></description>
			<content:encoded><![CDATA[<p><strong>Ulland Brothers will be paving the wear course on Woodland Avenue tomorrow morning, 10/24/09, between Kent Road and Clover Street.  This section of road will be closed during the morning and should be back open around 1:00 p.m.</strong>
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=60</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=58</link>
		<comments>http://saloeng.com/blog/?p=58#comments</comments>
		<pubDate>Tue, 13 Oct 2009 13:09:02 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=58</guid>
		<description><![CDATA[Progress
Ulland has completed all underground utility work for Phase I of the construction.  They have also finished subcutting from Griggs Place to Norton Street.  They are currently backfilling this area with sand and class 5.  Landscaping has been done between Clover Street and Griggs Place.  The curb &#038; gutter and sidewalk is complete up to [...]]]></description>
			<content:encoded><![CDATA[<p><u>Progress</u></p>
<p>Ulland has completed all underground utility work for Phase I of the construction.  They have also finished subcutting from Griggs Place to Norton Street.  They are currently backfilling this area with sand and class 5.  Landscaping has been done between Clover Street and Griggs Place.  The curb &#038; gutter and sidewalk is complete up to Griggs Place.</p>
<p><u>Schedule</u></p>
<p>Week of 10/12:  Continue backfilling road subcut; pave base course from Clover Street to Griggs Place.</p>
<p>Week of 10/19:  Finish concrete curb &#038; gutter and remaining driveways; place remaining base course from Griggs Place to Norton Street.</p>
<p>Week of 10/26:  Finish landscaping; place bituminous wear course; project clean-up.</p>
<p>Week of 11/2:   Remove detour; open roadway to public.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=58</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=53</link>
		<comments>http://saloeng.com/blog/?p=53#comments</comments>
		<pubDate>Thu, 17 Sep 2009 20:57:40 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=53</guid>
		<description><![CDATA[Greetings, everyone!
Salo Engineering, the City of Duluth, and Ulland Brothers are continuing their efforts to improve your neighborhood and business community.  We thank all residents and business owners for your support and patience during the construction season.
Progress
To date, Ulland has progressed quite well despite the rains in July and encountering ledge rock.  All the sanitary [...]]]></description>
			<content:encoded><![CDATA[<p>Greetings, everyone!</p>
<p>Salo Engineering, the City of Duluth, and Ulland Brothers are continuing their efforts to improve your neighborhood and business community.  We thank all residents and business owners for your support and patience during the construction season.</p>
<p><u>Progress</u><br />
To date, Ulland has progressed quite well despite the rains in July and encountering ledge rock.  All the sanitary sewer mains have been installed.  The watermain is complete, with the exception of the crossing at Elizabeth Street.  Storm sewer work and curb &#038; gutter up to Griggs Place are complete.</p>
<p><u>Remaining Schedule</u></p>
<p>Week of 9/21/09:    Ulland to continue on storm sewer work between Norton and Elizabeth Streets, place sidewalks from Clover Street to Griggs Place, shape class 5 for paving, and place water &#038; sanitary services from Griggs Place to Norton Street.  During this week, Ulland will be working on the storm sewer between St. Marie and Norton Streets.  This will require Woodland Avenue to be closed between those streets for 2-3 days.  Traffic will be able to cross Woodland Avenue at Norton Street, with a half-day closure to bring storm sewer across the intersection.  There will be temporary bituminous, curb, and sidewalk placed in this area, which will be removed next spring and rebuilt with the new roadway.</p>
<p>Week of 9/28/09:    Finish all storm sewer and utility services, pave bituminous from Griggs Place to Clover Street, and subcut roadway from Griggs Place to Norton Street.</p>
<p>10/5/09 – 10/30/09      Complete curb &#038; gutter, sidewalk, bituminous paving, and landscaping up to Norton Street.</p>
<p>11/1/09    Project under winter suspension and detour route is lifted.</p>
<p>5/1/10      Construction resumes and detour route is back in place.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=53</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=50</link>
		<comments>http://saloeng.com/blog/?p=50#comments</comments>
		<pubDate>Thu, 03 Sep 2009 16:07:45 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=50</guid>
		<description><![CDATA[Progress
During the last 2 weeks, Ulland has been working on the sanitary sewer main and watermain between Griggs Place and Norton Street.  The sanitary main is complete in this area, and the watermain is scheduled to be complete by September 11, 2009.  The intersection of Clover Street and Woodland Avenue has been opened, and the [...]]]></description>
			<content:encoded><![CDATA[<p><span style="text-decoration: underline">Progress</span></p>
<p>During the last 2 weeks, Ulland has been working on the sanitary sewer main and watermain between Griggs Place and Norton Street.  The sanitary main is complete in this area, and the watermain is scheduled to be complete by September 11, 2009.  The intersection of Clover Street and Woodland Avenue has been opened, and the signal system is operational.<span style="text-decoration: underline" /></p>
<p><span style="text-decoration: underline">Schedule</span></p>
<p>Following is an update of the remaining schedule:</p>
<p>September 8-12:  Ulland will finish watermain work up to Norton Street and begin placing water and sewer services from Griggs Place to Norton Street.</p>
<p>September 14-19:  Storm sewer will be placed from Elizabeth Street to St. Marie Street.  Hovland Masonry will place curb &#038; gutter and sidewalk from Clover Street to Griggs Place.  The high pressure watermain crossing at Elizabeth Street will be done.  We will notify affected parties 48 hours in advance of the watermain shutdown.</p>
<p>September 21-26:  Ulland will be rebuilding the roadway from Griggs Place to Norton Street.</p>
<p>September 28 - October 24:  Remaining curb &#038; gutter and sidewalks will be placed, along with bituminous paving and landscaping.</p>
<p>The contractor has a completion date of November 1, 2009 for this segment of the project.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=50</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=48</link>
		<comments>http://saloeng.com/blog/?p=48#comments</comments>
		<pubDate>Wed, 19 Aug 2009 16:35:38 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=48</guid>
		<description><![CDATA[Progress
This past week, ledge rock was encountered in the sanitary sewer trench between Elizabeth and Norton Streets.  Ulland continues to move slowly through the rock section with the sanitary sewer.  In addition, Ulland has begun placing watermain from Griggs Place north toward Elizabeth Street.  We anticipate some small disruptions in water service between Elizabeth and [...]]]></description>
			<content:encoded><![CDATA[<p><span style="text-decoration: underline">Progress</span><br />
This past week, ledge rock was encountered in the sanitary sewer trench between Elizabeth and Norton Streets.  Ulland continues to move slowly through the rock section with the sanitary sewer.  In addition, Ulland has begun placing watermain from Griggs Place north toward Elizabeth Street.  We anticipate some small disruptions in water service between Elizabeth and St. Marie Streets.  All affected parties will be notified at least 24 hours in advance of any disruption.  Salo Engineering and the City of Duluth Engineering Department continue to keep the Duluth Fire Department informed about accessibility to the east end of Elizabeth Street.  At the request of several business owners, we ordered a construction sign with all business names in the Mount Royal Center.  This sign will be displayed at the intersection of St. Marie Street and Woodland Avenue.  As construction progresses toward St. Marie Street, the sign will be moved accordingly.</p>
<p><span style="text-decoration: underline">Schedule<span style="text-decoration: underline"><span style="text-decoration: underline" /></span></span></p>
<p>There are no changes to the project schedule posted last week.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=48</wfw:commentRss>
		</item>
		<item>
		<title>Woodland Avenue Project Update</title>
		<link>http://saloeng.com/blog/?p=46</link>
		<comments>http://saloeng.com/blog/?p=46#comments</comments>
		<pubDate>Thu, 13 Aug 2009 13:24:31 +0000</pubDate>
		<dc:creator>saloadmin</dc:creator>
		
		<category>Uncategorized</category>

		<guid isPermaLink="false">http://saloeng.com/blog/?p=46</guid>
		<description><![CDATA[Progress:
Ulland has made great progress on Woodland Avenue.  We opened the roadway from Kent Road to College Street on August 6th.  College Street to Clover Street will open the first week of September prior to the opening of Woodland Middle School.  The signal system at Kent Road was turned back on this week.  Ulland began the [...]]]></description>
			<content:encoded><![CDATA[<p>Progress:</p>
<p>Ulland has made great progress on Woodland Avenue.  We opened the roadway from Kent Road to College Street on August 6th.  College Street to Clover Street will open the first week of September prior to the opening of Woodland Middle School.  The signal system at Kent Road was turned back on this week.  Ulland began the work on the sanitary sewer from Norton Street to Griggs Place early this week.  They will continue with the sanitary until it is complete, then switch to the water main construction.  Ulland is also building the road section from Clover Street to Griggs Place.  We have kept the pavement at the Elizabeth Street intersection as long as possible.  This will be removed within a week.  When work starts in the intersection of Elizabeth Street, the contractor has been directed to keep one lane of traffic open at all times.  Salo Engineering has invited the Duluth Fire Department to attend the last three construction meetings.  We have kept them informed of the upcoming construction activities and the accessibility to the end of Elizabeth Street.</p>
<p>Schedule:</p>
<p>Here is a quick look at the remaining work items.</p>
<p>August 13-28 - Ulland will be placing water main, sanitary sewer &#038; services between Norton Street and Griggs Place.  They will also be building the roadway section from Clover Street to Griggs Place.</p>
<p>September 1-11 - Ulland will be placing new storm sewer from Norton Street to Griggs Place.</p>
<p>September 14-25 - Ulland will be rebuilding the roadway from Norton Street to Griggs Place.</p>
<p>Curb &#038; gutter, sidewalks, bituminous paving, and landscaping will start in middle of September.  These operations will continue through October.  The contractor has a completion date of November 1, 2009 for this segment of the project.
</p>
]]></content:encoded>
			<wfw:commentRss>http://saloeng.com/blog/?feed=rss2&amp;p=46</wfw:commentRss>
		</item>