Fri 6 Aug 2010
Greetings, Everyone!
We are now halfway through the 2010 construction season. After working through the contaminated soil in the intersection of St. Marie Street and Woodland Avenue, we have finally placed curb & gutter and sidewalk and paved this area. This has allowed us to move into Phase II of the 2010 detour route, which directs traffic from Arrowhead Road to Wallace Avenue to St. Marie Street and then back to Woodland Avenue.
Remaining Work Schedule: Ulland Brothers will continue working on water and sewer services and then move to the storm sewer. This work will take about 4 more weeks. After that, they will begin rebuilding the roadway and finally concrete and landscaping. We are anticipating a completion date of early October.
A reminder that we continue to hold weekly construction meetings on Tuesdays at 9:00 a.m. at the intersection of St. Marie Street and Woodland Avenue. If anyone has any questions, please contact David Bolf at 727-8796.